Marine works at north-eastern corner of New Yau Ma Tei Typhoon Shelter

21 Sep 2021 / Hong Kong

For approximately 12 months, marine works involving the delivery of prefabricated segments by a crane barge and one tugboat; and establishment of additional layer of silt curtains by one work boat will be carried out within the area bounded by straight lines joining the following co-ordinates (WGS 84 Datum) from (A) to (D) and the adjacent shoreline:
(A) 22º 18.980’N / 114º 09.575’E
(B) 22º 18.975’N / 114º 09.561’E
(C) 22º 18.998’N / 114º 09.551’E
(D) 22º 19.010’N / 114º 09.556’E

Silt curtains will be established near the outlet of the Cherry Street box culvert at north-eastern corner of New Yau Ma Tei Typhoon Shelter, with two ends fixed on vertical seawall, to intercept general floating refuse from the culvert. Yellow marker buoys fitted with yellow flashing lights will be laid along the surface of the silt curtains to mark the extent of the silt curtains.

The hours of work will be from 0800 to 1800 hours. No works will be carried out on Sundays and public holidays. Vessels employed for the works will stay in the works area outside the hours of work.

Diving operations will be carried out from time to time during the hours of work.

Vessels engaged in the operations will display signals as prescribed in international and local regulations.

Vessels navigating in the vicinity should proceed with caution and keep clear of the works area at slow speed, bearing in mind there are divers working in the area.

(For information about operations in Hong Kong, contact GAC Hong Kong at [email protected])

Source: Government of the Hong Kong SAR Marine Department Notice No.157/2021