Reconstruction works for Kau Sai Village Pier, Sai Kung

18 Feb 2022 / Hong Kong

For approximately 24 months, reconstruction works for Kau Sai Village Pier will be carried out within the area bounded by straight lines joining the following co-ordinates (WGS 84 Datum) from (A) to (F) and the adjacent shoreline:
(A) 22º 20.550’N / 114º 19.244’E
(B) 22º 20.541’N / 114º 19.253’E
(C) 22º 20.519’N / 114º 19.253’E
(D) 22º 20.519’N / 114º 19.186’E
(E) 22º 20.557’N / 114º 19.186’E
(F) 22º 20.557’N / 114º 19.197’E

The works will be carried out by one dumb lighter. One crane barge and one tugboat will provide assistance.

A working area of approximately 30 metres around the lighter will be established. Yellow marker buoys fitted with yellow flashing lights will be laid to mark the positions of the anchors extending from the lighter.

Silt curtains fitted with yellow flashing lights will be established within the works area. The silt curtain is a large piece of netting used to contain mud and sediment.

The hours of work will be from 0800 to 1800 hours. No works will be carried out on Sundays and public holidays. Vessels employed for the works will stay in the works area outside the hours of work.

Diving operations will be carried out from time to time during the hours of work.

Vessels engaged in the operations will display signals as prescribed in international and local regulations.

Vessels navigating in the vicinity should proceed with caution and keep clear of the works area at slow speed, bearing in mind there are divers working in the area.

(For information about operations in Hong Kong, contact GAC Hong Kong at [email protected])

Source: Government of the Hong Kong SAR Marine Department Notice No.31/2022

If quoting any content from Hot Port News, please cite GAC Hot Port News as the source.